(영문) 대구지방법원 2017.09.14 2016가합2998

용역비

Text

1. The Defendant’s KRW 715,00,000 as well as the Plaintiff’s annual rate of 6% from January 8, 2015 to August 25, 2016, and the following.

Reasons

. The Promotion Committee for the Establishment of the Consolidation Project Association (hereinafter referred to as “A”) and the S square C&D architect (hereinafter referred to as “Plaintiffs and hereinafter referred to as “B”) shall prepare two copies of this Agreement in order to conclude and prove that the contract for the special management of the rearrangement project on behalf of others such as authorization and permission following the implementation of the Housing Redevelopment Project and keep one copy after signing and sealing respectively.

- - sound;

1. Project name) Project name: A district redevelopment and rearrangement project B: A district redevelopment and rearrangement project: The housing redevelopment and rearrangement project under the Act on the Maintenance and Improvement of Urban Areas and Dwelling Conditions for Residents; the area of housing site B in Nam-gu, Daegu-gu;

2. Contents of a contract: Agency business under Article 69 of the Act on the Improvement of Urban and Residential Environments;

3. Contract period: From the contract date to the completion of the project; and

4. Total service amount A) Total amount: A loan interest rate of KRW 5 billion in total (1.3 billion in value-added tax separately): A fixed interest rate of KRW 5% per annum : A fixed interest rate for the redevelopment and improvement project agency service contract; Article 1 through Article 7 (Omission of Payment Method and Time of Service Costs) (1) of the terms and conditions of the contract for the redevelopment and improvement project for housing redevelopment and improvement project; “A” shall pay the progress payment for the service cost to “B” in accordance with the following payment dates and payment rates:

In principle, the payment method shall be deposited into the corporate passbook of "B".

(2) The total service cost of agency business shall be KRW 1.3 billion per day (excluding value-added tax).

3. “A” shall not delay the payment of the progress payment for the service cost if the “B” claims the progress payment for the service cost according to the following due date, and if the payment period exceeds the due date, the “B” may charge the statutory interest for arrears.

(4) Time and rate of payment shall be as follows:

The second payment period is to be settled after the selection of the contractor within 15 days after the date of the first payment, and the second payment period is to be completed after the completion of the designation of the rearrangement zone.