beta
(영문) 부산지방법원 2017.01.24 2016가단52704

대여금

Text

1. The Defendant shall pay to the Plaintiff KRW 102,00,000 and the interest rate of KRW 15% per annum from September 6, 2016 to the date of complete payment.

Reasons

1. Indication of claims: To be as shown in the attached Form;

2. The judgment by service by public notice (Article 208(3)3 of the Civil Procedure Act): Provided, That the Plaintiff claims damages for delay at the rate of 20% per annum from September 6, 2016 to the date of full payment. However, the provisions on statutory interest rate under the main sentence of Article 3(1) of the Act on Special Cases Concerning Expedition, etc. of Legal Proceedings were amended by Presidential Decree No. 26553, Oct. 1, 2015 to 15% per annum, and thus, the Plaintiff’s damages for delay claimed in excess is dismissed.