대여금
1. The defendant shall pay to the plaintiff KRW 40,054,740 as well as KRW 40,00,000 among them, from August 1, 2005 to October 28, 2008.
1. Indication of claims: To be as shown in attached Form of claims;
(However, the creditor is the plaintiff and the debtor is the defendant). 2. Service by public notice (Article 208 (3) 3 of the Civil Procedure Act)
3. Grounds for partial dismissal: The portion of a claim for delay damages exceeding the respective ratio of 15% per annum from October 1, 2015 and 12% per annum from June 1, 2019 to October 1, 2015, which was wholly amended by Presidential Decree No. 26553, Sept. 25, 2015; and which was partially amended by Presidential Decree No. 29678, May 21, 2019; and was in force on June 1, 2019) of the Plaintiff’s claim for delay damages is dismissed.