beta
(영문) 대전지방법원 2015.09.09 2015가합1875

대여금

Text

1. The Defendant shall pay to the Plaintiff KRW 232,50,000 and the interest rate of KRW 24% per annum from April 4, 2015 to the date of complete payment.

Reasons

1. Indication of claim;

A. On July 3, 2014, the Plaintiff lent KRW 232,50,000 to the Defendant at interest rate of 24% per annum (payment on the third day of each month) and on September 12, 2014.

B. However, the Defendant paid only interest on the above loan until April 3, 2015.

C. Therefore, the Defendant is obligated to pay to the Plaintiff damages for delay at the rate of 24% per annum from April 4, 2015 to the date of full payment, which is the day following the date of the last payment of interest, to the day of full payment.

2. Article 208 (3) 1 of the Civil Procedure Act of the applicable provisions of Acts;