beta
(영문) 대전지방법원 2016.02.26 2015가단30104

물품대금

Text

1. The Plaintiff:

A. The defendant limited liability company A shall be KRW 46,00,000 and it shall be from September 1, 2015 to September 30, 2015.

Reasons

Comprehensively taking account of the overall purport of the arguments as to Gap evidence Nos. 1 and 2, the plaintiff supplied the defendant limited liability company Eul (hereinafter "the defendant company") with the "fence" until January 30, 2015, but did not receive KRW 46 million out of the price of the goods. The defendant Eul guarantees joint and several liability of KRW 23 million out of the price of the goods to the plaintiff of the defendant company.

According to the above facts of recognition, Defendant Company is obligated to pay to the Plaintiff the amount of KRW 46 million, the amount of KRW 23 million jointly and severally with Defendant Company, and each of the above amounts of money, 20% per annum from September 1, 2015 to September 30, 2015, which is the day following the delivery of a copy of the complaint against the Defendants, and 15% per annum under the Act on Special Cases Concerning Expedition, etc. of Legal Proceedings from the next day to the day of full payment.

Therefore, the plaintiff's claim of this case is reasonable, and it is decided as per Disposition by admitting it.