손실보상금증액 청구
1. The Defendant’s KRW 1,259,309,529 for the Plaintiff and 5% per annum from August 19, 2015 to July 11, 2017 for the Plaintiff.
1. Details of ruling;
(a) Project approval and public announcement - Project name: Public housing project (B) - Public housing project: The defendant; < Amended by Presidential Decree No. 18790, Dec. 23, 2005>
B. The Central Land Tribunal’s ruling on expropriation by June 25, 2015 - Land subject to expropriation by the Central Land Tribunal (hereinafter “each land of this case”) and the land obstacles thereto, business facilities, and trees (hereinafter “waters of this case”): Compensation for losses: The specific details of each land of this case, including KRW 1,375,135,200, total amount of compensation for losses, and total amount of compensation for business, KRW 1,236,491,00,000.
As set out in the detailed contents.
- Commencement date of expropriation: An appraisal corporation on August 18, 2015 - An appraisal corporation, one appraisal corporation, and a national appraisal corporation;
(c) - Compensation for losses on November 19, 2015 - The Central Land Tribunal shall dismiss the objection as to each of the instant lands 1,394,647,670, and the total amount of obstacles - The appraisal corporation shall be referred to as "appraisal" among the above appraisers, and the results of appraisal shall be referred to as "appraisal"; 3218,790,790, 300, 36466, 300, 318, 300, 311, 60, 600, 250, 467, 8664, 67, 367, 286, 47, 967, 196, 196, 467, 196, 196, 196, 196, 196, 196, 207, 207, 367, 467, 167
D. Each of the instant lands in this case: The land subject to expropriation of KRW 2,400,956,500 (Seoul Metropolitan City D) is subject to the commission of appraisal of appraiser M: the land category size (land size) of the original land area (land size).