(영문) 서울중앙지방법원 2016.06.03 2015가합27298

대여금

Text

1. As to KRW 50,00,000 and KRW 500,000 among them, the Defendant shall pay to the Plaintiff the year from January 2, 2014 to March 13, 2016.

Reasons

1. The description of the grounds for the claim shall be as specified in the attached Form;

(However, “creditor” is “Plaintiff,” and “debtor” is “Defendant.”

2. Judgment without holding any pleadings (Articles 208 (3) 1 and 257 (1) of the Civil Procedure Act);

3. The Plaintiff partially dismissed shall claim damages for delay calculated at the rate of 20% per annum from the day after the original copy of the instant payment order was served to the day of complete payment.

However, the provision on statutory interest rate under the main sentence of Article 3(1) of the Act on Special Cases Concerning Expedition, etc. of Legal Proceedings (Presidential Decree No. 26553, Sept. 25, 2015) that reduces the statutory interest rate from 20% per annum to 15% per annum under the main sentence of Article 3(1) of the Act on Special Cases Concerning Expedition, etc. of Legal Proceedings (Presidential Decree No. 26553, Sept. 25, 2015) was amended and promulgated as of Sept. 25, 2015, and came into force from October 1, 2015, the delay damages from the day after the original copy of the instant payment order was served on March 13, 2016 to