유치권확인 청구의 소
1. As to the buildings listed in the separate sheet:
A. 124,240,530 won and 30.0 of them to be known to the central government of the Plaintiff.
1. Basic facts
A. D Co., Ltd. (hereinafter “D”) newly constructed a building listed in the attached list (hereinafter “instant factory”) on the ground of Chungcheong City, E, and obtained approval for use from the Chungcheong City Mayor around June 30, 201, and completed registration of initial ownership on July 25, 201.
B. On January 8, 2013, the Small and Medium Business Corporation, the mortgagee of the right to collateral security, filed an application for commencement of voluntary auction with the Cheongju District Court AssistanceF for the instant factory, and received a decision on voluntary commencement of auction from the above court, and on January 10, 2013, registered the decision on voluntary commencement of auction on the instant factory.
(hereinafter “instant auction procedure”). C.
In the instant auction procedure, the Plaintiffs reported the lien on March 6, 2013, and ② the Defendant was awarded the instant factory contract on October 31, 2013.
(3) On September 28, 2011, Plaintiff 2: (a) filed a new construction suit against Plaintiff 2, 20,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,00,00,03,00.