beta
(영문) 의정부지방법원 고양지원 2018.10.24 2018가단6115

건물명도 등

Text

1. From September 15, 2018 to September 15, 2018, the Defendant is from the Plaintiff’s KRW 3,5250,00 to the completion date of delivery of the building indicated in the attached sheet.

Reasons

According to the overall purport of Gap evidence Nos. 1 through 5 (including branch numbers) and the entire pleadings, the plaintiff leased the building as indicated in the attached Form (hereinafter referred to as "the building in this case") to the defendant on September 2, 2015 by setting the deposit of KRW 50 million, monthly rent of KRW 3520,000,000, and the period of June 14, 2017. The defendant operated the restaurant in this case, operated the restaurant in this case on June 15, 2017, and increased the rent of KRW 3.85,00,000,000,000,000,000,000,000,000,0000,000,000,0000,000,000,0000,000,0000,000) from May 16, 2016.

4. Until May 2, 2018, the fact that the Defendant notified that the rent in arrears should be paid in full and if so, the lease contract will be terminated; the Defendant’s KRW 14 million on May 2, 2018; and

6.21.1 million won, per year;

8. The payment of KRW 9 million on September 17, 199 and KRW 11 million on September 21, 2018 can be recognized as having caused delay until September 14, 2018, and there is no counter-proof.

According to the above facts, the Defendant is obliged to pay the Plaintiff the remaining money calculated by deducting the money calculated by the rate of KRW 3850,000 per month from September 15, 2018 to the completion date of delivery of the building of this case from the date following the day when the last rent was paid at KRW 35,250,000 ( KRW 50,000 - 14,7550) of the remaining lease deposit from the Plaintiff and at the same time to deliver the building to the Plaintiff.

The plaintiff's claim is justified, and it is so decided as per Disposition.