대여금
1. The Defendant shall jointly and severally with C to the Plaintiff KRW 27,50,000 and 5% per annum from November 13, 2015 to May 14, 2016.
1. Indication of claim;
A. On March 17, 2015, C prepared a certificate of loan between the Plaintiff and the Plaintiff that “to borrow KRW 30,000,000 from the Plaintiff, but to repay KRW 37,50,000 including interest until September 17, 2015,” and the Defendant jointly and severally guaranteed the Plaintiff’s obligation to borrow money.
B. On March 17, 2015, the Plaintiff transferred KRW 30,000,000 to the Defendant’s account. However, the Defendant and C paid only KRW 10,000 to the Plaintiff on November 12, 2015, the Defendant is jointly and severally liable with C to pay the remainder of KRW 27,50,000 to the Plaintiff and the delay damages.
2. Article 208 (3) 3 of the Civil Procedure Act applicable provisions of Acts.