beta
(영문) 서울중앙지방법원 2016.07.15 2015가합557133

공탁금출급청구권확인

Text

1. The National Agricultural Cooperatives Federation deposited by the Incheon District Court No. 5536 on September 3, 2012 821,891,560 won, among the 821,891,560 won.

Reasons

Basic Facts

The status of the parties to the National Agricultural Cooperative Federation (hereinafter referred to as the “CF”) is the ordering person who has awarded a contract for the construction of the Domart Port Construction Co., Ltd. (hereinafter referred to as the “Domsan Construction”) to the Domsan Construction Co., Ltd. (hereinafter referred to as the “Domsan Construction”), and the Plaintiff is the bankruptcy trustee who has the right to manage and dispose of the property belonging to the bankrupt foundation by declaration of bankruptcy regarding the Domsan Construction. The Defendants are the subcontractors who received part of the above construction from the Domsan Construction, or the suppliers of materials

On April 26, 2010, 2010, it was confirmed that agricultural cooperatives were obligated to pay KRW 821,891,560 to the construction cost in addition to the progress payment already paid by agricultural cooperatives as a result of the settlement of construction completion.

On July 3, 2012, 2012, the Agricultural Cooperative was decided to commence rehabilitation proceedings as Seoul Central District Court 2012 Gohap116, which was prior to the actual payment of the balance due to the financial shortage, and on April 16, 2014, the above rehabilitation proceedings were abolished and the Seoul Central District Court was declared bankrupt as Seoul District Court 2014Hahap63.

The names of the Parties (hereinafter referred to as "Defendant Co., Ltd.") are omitted on April 28, 201, 201, 914, 100, 200, 200, 200, 361, 000, 206. 7. 8. 6. 8. 6. 8. 6. 6. 4, 200, 200, 200 4. 7. 6. 8, 207, 208, 206. 4. 7. 8, 207, 206. 4. 8, 207, 206. 4. 8, 207, 206. 4. 8, 201, 47, 142, 000, 542, 184, 184, 2015