(영문) 서울북부지방법원 2015.12.02 2014가합25911
공사대금
Text
1. The plaintiff's claim is dismissed.
2. The costs of lawsuit shall be borne by the Plaintiff.
Reasons
The statement in Gap evidence No. 1 alone is insufficient to recognize that the plaintiff completed the remodeling construction of the building in the Bupyeong-gu B building subcontracted by the defendant around October 2013, and that the unpaid construction cost is KRW 125 million, and there is no other evidence to acknowledge otherwise.
Therefore, the plaintiff's claim for the construction cost of this case is groundless, and thus dismissed.