(영문) 창원지방법원 2016.04.05 2015가단24822

공사대금

Text

1. The Defendant shall pay 2,5410,00 won to the Plaintiff and 15% per annum from November 14, 2015 to the date of full payment.

Reasons

1. On September 2014, the Plaintiff completed the construction by being awarded a contract for the construction cost of KRW 180,000,000,000 for the Han River Sewerage Maintenance Work (hereinafter “instant construction work”). On October 15, 2014, the Plaintiff settled the construction cost of this case between the Defendant and the Defendant in KRW 127,60,00 (Additional Tax separate). The Plaintiff received the construction cost of this case from the Defendant in KRW 14,50,000 (Additional Tax separate) is not in dispute between the parties, or comprehensively taking into account the purport of arguments as to the Plaintiff’s statement No. 1 through No. 55,00,000,000 from the date of the Han River Sewerage Maintenance Work. According to the above recognition facts, the Defendant is liable to pay the Plaintiff the remainder of KRW 2541,510,000 (including the Plaintiff’s additional tax) out of the settlement amount, and damages for delay from 151,145.

2. The defendant's assertion is asserted that the defendant suffered losses, such as decline in foreign credit, in addition to the cost expenditure and loss of expectation profits, due to the lack of technical capabilities of the plaintiff's input personnel and the lack of the performance of the plaintiff's input equipment at the construction site of this case on November 2014. However, the defendant's assertion is not accepted, since there is no evidence to acknowledge it.

3. Conclusion, the plaintiff's claim is justified and acceptable.