공사대금
1. The Defendant: (a) to Plaintiff Daelim Industry Co., Ltd.; (b) KRW 8,149,470,420; and (c) 1,301,729.
The summary of the instant case is to omit the indication of the Plaintiffs’ “stock company” from the time of the second referring to the Plaintiff Daelim Industry Co., Ltd. (hereinafter referred to as “Co., Ltd.”) to the period of construction extended by 1 and 2 times by a general contract with respect to the Plaintiffs’ contracts for construction of the Gwangju National Asian Culture Complex by a long
() The case is that the Plaintiff Company sought the payment of the indirect construction cost incurred additionally during the period from May 31, 2012 to October 31, 2014, the Plaintiff Company Samwon Power Co., Ltd., Ltd., and from June 24, 2012 to October 31, 2014).
In fact, the construction contract was concluded between the plaintiffs (contractor) and the defendant (contractor) by the method of long-term contract with respect to construction works, machinery and equipment works, and electrical construction works among the construction works of the Gwangju National Asian Culture Complex (Demand Agency: Ministry of Culture, Sports and Tourism) as listed below.
Of them, in the case of electrical construction, the plaintiff Samwon Power and the joint supply and demand company (representative: plaintiff Samwon Power) was organized and awarded a contract.
On April 16, 2008, Plaintiff Daelim Industry 157,428,526,000 (1,500 days after commencement of construction) from April 21, 2008 to May 30, 2012, 209, Plaintiff Scagle 29,407,240,683, May 1, 2009 to May 30, 2012 (1,125 days after commencement of construction work) constructed on April 30, 208 (1,125 days after commencement of construction work) on March 18, 2009, the construction work of Plaintiff Scacle 29,407,240,683 from May 1, 209 to May 30, 2012 (1,125 days after commencement of construction work) was executed on September 30, 208.
On August 25, 201, 1201, the contract period (cost) contract period of a sewage supplier, which is the date of a contract, for the construction work, the Suwon Construction Co., Ltd. 3,329,700,000 from August 25, 201 to November 16, 2012, the reinforced concrete construction Co., Ltd. 8,888,000,000 for a reinforced concrete construction-1 construction site Co., Ltd. from August 17, 201 to November 16, 2012. < Amended by Act No. 11013, Aug. 17, 2011; Act No. 11500, Oct. 12, 2010; Act No. 11388, Oct. 3, 2012>