(영문) 대구지방법원 2018.01.16 2016구합20465

관리처분계획취소

Text

1. The Defendant’s management and disposition plan approved by the head of the Daegu Metropolitan City on November 27, 2015 shall be revoked.

2...

Reasons

1. Details of the disposition;

A. The Defendant: (a) is a rearrangement project association that implements a housing reconstruction improvement project (hereinafter “instant project”) with a size of 19,348.6 square meters in Daegu Jung-gu as a rearrangement zone; (b) obtained authorization from the head of Jung-gu Seoul Metropolitan City (hereinafter “the head of Jung-gu”) on March 9, 2005; and (c) obtained authorization to implement a project implementation on September 7, 2005; and (d) requested one appraisal corporation (hereinafter “one appraisal corporation”) and a dialogue appraisal corporation (hereinafter “large-gu appraisal corporation”) to conduct an appraisal of the land and buildings within the instant project area (hereinafter “previous appraisal”) on September 2, 2005; (c) however, the dialogue appraisal corporation prepared an appraisal report on the said subject matter as of September 12, 2005, which is the announcement date of authorization to implement the project implementation around the end of April 206.

B. On April 16, 2007, the Defendant obtained authorization from the head of the Gu for the management and disposal plan formulated based on the previous appraisal, but on June 11, 2015, obtained authorization for the change of the project implementation as follows.

Details on September 7, 2005 project implementation authorization: 19,316§³ (other than H 204 lots) 19,348.60С on June 11, 2015 (other than H 198,161,127,80С) 20.27% of building site size 20.15% of 283.19% of 27.19% of the height of 27.27.10% of 27.2444.67.67,739.67,987,987,48.47.2544.75.75,298.47.2544.67.25.29442.67.520,000 square meters of 29.67,000 square meters of 29.67,000 stories of underground 24.24,000 square meters of residential household.

C. The defendant is above.