업무용역비
1. The plaintiff's claim is dismissed.
2. The costs of lawsuit shall be borne by the Plaintiff.
The basic facts are an organization established for the purpose of establishing a regional housing association under the Housing Act to promote the project (hereinafter referred to as the “project in this case”) by developing 12 L of the housing site district in Ulsan-gu, Ulsan-do (hereinafter referred to as the “project site”) and constructing multi-family housing (hereinafter referred to as the “project in this case”).
On October 20, 2014, the Plaintiff entered into an agency contract (hereinafter “instant agency contract”) with the Promotion Committee to which the authority necessary for the instant project implementation is delegated to the Plaintiff by the Promotion Committee, including overall business affairs, site location review, and feasibility review related to the purchase of the instant project site (hereinafter “instant agency contract”).
The main contents of the instant agency contract are as follows.
The committee for promotion of agency contracts and the plaintiff shall conclude an agency contract as follows for the effective and successful promotion of the project of this case on the project site of this case.
Article 2 (Division of Work)
1. For the prompt and normal performance of the project, the promotion committee and the Plaintiff shall share their respective duties in good faith and shall cooperate with each other, and shall be responsible therefor.
2. The promotion committee shall faithfully implement the following:
(1) (2) Purchase of the project site (3) the recruitment of members of the association (4) the allocation of all the project costs related to the project, (5) the selection of all the service companies related to the project and the conclusion of the contract (7) the designation of the service companies related to the project and the determination thereof, including the above work, shall be supported and delegated en bloc to the Plaintiff.
3. The Plaintiff is delegated with the duties of the promotion committee under paragraph (2) and faithfully implement the following matters.
(1) Overall and overall business activities relating to the purchase of the project site; and