(영문) 서울중앙지방법원 2014.08.20 2013가합58397

공사대금

Text

1. The Defendant’s KRW 432,080,128 as well as 6% per annum from August 6, 2013 to August 20, 2014.

Reasons

1. Facts of recognition;

A. On July 13, 2012, the Plaintiff received subcontracting each of the terms of KRW 2,362,90,000 for the Iron Corporation (which is related to the building and parking lot building of this building; hereinafter collectively referred to as the “instant construction”) among the “B hospital alteration and remodeling construction” in the Sinpo City A from the Defendant on July 13, 2012 (i.e., KRW 1,976,589,467 for the instant construction (i.e., the instant construction) (i., indirect costs of KRW 136,571,204 for the parking lot of KRW 36,839,329, value-added tax of KRW 212,90,000 for the parking lot of KRW 212,90,00 for the value-added tax of KRW 329,329,00 for the period from July 13, 2012

(hereinafter referred to as the “contract that forms the basis of the said subcontract”. B.

In the instant contract, the parking lot building was agreed to be constructed up to 6th floor. After the Defendant’s request, the Plaintiff constructed the parking lot building up to 7th floor, and changed detailed materials necessary for the construction of the parking lot building differently from those stipulated at the time of the instant contract. At the Defendant’s request, the Plaintiff also additionally constructed the “fire sprinking and cutting sprinkling construction,” “Recordinging and cutting sprinking construction,” and “construction works for high-calorie smoking.”

(The specific basis for determining the scope of the instant construction and the additional construction is as described in Section 2(b) below.

On March 29, 2013, the Plaintiff completed the instant construction project and the instant additional construction project required by the Defendant.

As above, since a parking lot building has been constructed up to seven floors and detailed materials have been modified and constructed, the construction cost for the part of the parking lot building shall be KRW 2,34,726,405, and the construction cost for fireproof and heating repair work for this building shall be KRW 22,596,936 (including construction cost for the new storage facility) and KRW 8,258,426, and the Defendant recognized that the construction cost for the new storage facility is KRW 16,481,154, while the Defendant recognizes that the construction cost for the new storage facility is KRW 16,481,154.

[Reasons for Recognition] Class A, Nos. 1, 5, 6, 7, 10 through 16, 18, 19, 20.