(영문) 서울중앙지방법원 2013.08.13 2012가합24274

하자보수금 등

Text

1. The part of the Plaintiff’s claim for damages in lieu of defect repairs against Defendant GaS Construction Co., Ltd.

Reasons

1. Basic facts

A. Status 1 of the parties concerned) The plaintiff is A apartment (30 units of Dong, 1,875 units of Dong, 1,875 units of Dong, hereinafter "the apartment of this case") on the ground B of Asan City.

(2) The Korea Land Trust Co., Ltd. (hereinafter referred to as the “Korea Land Trust”) is a project proprietor who constructed and sold the instant apartment, and the Defendant Land Trust Co., Ltd. (hereinafter referred to as the “Defendant Land Trust”) is a new construction contractor of the instant apartment after being awarded a contract with the Defendant Korea Land Trust to construct the instant apartment from the Defendant Korea Land Trust.

3) Defendant Seoul Guarantee Insurance Co., Ltd. (hereinafter “Defendant Seoul Guarantee Insurance”).

(2) The Defendant SP has guaranteed the obligation to repair the defects of the apartment of this case. B. From December 27, 2007 to December 26, 2008, 2,71,271,870,402D 2D 26 December 27, 2007 to December 26, 2007 to December 26, 2007 to the Seoul 2,271,870,402 E E. 3, 207 to December 27, 2007 to the 205, 207, 3,407, 807, 605, 603, 604, 603, 407, 207, 207, 207, 205, 207, 207, 207, 307, 201, 207, 207, 27, 27, 201.

2. According to the terms and conditions of each guarantee insurance contract of this case, the Defendant Seoul Guarantee Insurance Co., Ltd., the policyholder, is a contract or a sales contract.