공사대금
1. The plaintiff's claim is dismissed.
2. The costs of lawsuit shall be borne by the Plaintiff.
1. Basic facts
A. On April 6, 2007, the party’s relation Samdo Construction Co., Ltd. (hereinafter “TM Construction”) entered into a standard contract for private construction works with BM Construction Co., Ltd. (hereinafter “NonM Construction”) and attached hereto.
1. The contractor is the company that purchased part of the instant land on October 30, 2014.
B. On April 6, 2007, 33,958,200,000 won (in addition to value-added tax, various kinds of personal construction cost), advance payment 2,00,000 won, and entered into the instant contract and received 2,00,000,000 won advance payment from MM construction.
C. The failure to pay the construction cost of the IM Construction) was under way of the construction of the instant construction, the construction of the instant construction, the engineering works, and steel framed works, and the construction in accordance with the revised design drawing was requested by IM Construction, and on December 2, 2007, it was required to increase the contract amount according to the alteration of design of the instant construction. Around February 2008, while the determination of the contract amount was delayed, it became impossible to pay the construction cost after being notified by the creditors of the loss of benefit due to the change of design. (ii) Cridge Construction was under the circumstance of being unable to pay the construction cost upon being notified by the creditors on February 27, 2008. As of February 27, 2008, when IM Construction faces insolvency, it was calculated at KRW 11.60%, the construction cost was calculated at KRW 4.2 billion, and the construction payment was not made, but the payment was not made.
On March 1, 2008, the construction of this case was suspended on March 1, 2008.
(e).