(영문) 대전지방법원서산지원 2017.09.12 2016가단55624

공사대금

Text

1. The Defendant’s KRW 23,00,000 as well as annual 5% from March 22, 2016 to September 12, 2017 to the Plaintiff.

Reasons

1. Facts of recognition;

A. On August 29, 2015, the Plaintiff entered into a contract with the Defendant for the new construction of the instant housing C-S-S-S-S-S-S-S-S-S-S-S-S-S-S-S-S-S-S-S-S-S-S-S-S-S-S-S-S-S-S-A (hereinafter “instant construction”).

The main contents are as follows:

Scope of construction

1. Construction of main building and main entrance and exit;

2. The report on the establishment and use of the front DNA food and stone of the building;

3. Heating and cooling works;

4. Main stairs and outer retaining walls may be changed according to the situation of the site;

5. Development of external windows, solar KCC or the specifications of the said level;

6. Scope of failure to perform the works to change the appearance of the roof or roof roof roof;

1. Arrangement of sites outside construction sites;

2. Direct creation of the owner of a building after the change into an external gravel turfy;

3. In addition to the particulars and the portion requested by the owner, the work progress after submitting and obtaining an estimate and obtaining approval - The plaintiff will undertake the work in accordance with the terms and conditions of this contract (including drawings, specifications, construction specifications, etc.; hereinafter the same shall apply) and the design documents (including drawings, specifications, construction specifications, etc.) in principle, the part not specified in the design documents shall be determined by mutual agreement

Article 3 (Implementation of Construction Works)

1. The plaintiff shall carry out the construction work in accordance with the separate drawing and drawing, and may not modify the design contents at will without the consent of the defendant.

Article 5 (Payment of Price) The Defendant shall pay the Plaintiff the price of KRW 228 million.

1. Contract deposit of 70 million won (in the case of a contract),

2. Part-time payment of KRW 190 million (after the completion of framework works);

3. An intermediate payment of KRW 245 million (after completion of external finishing works);

4. Any balance shall be paid in installments as at the rate of 23 million won (at the time of completion of construction works).

B. The Plaintiff completed the instant construction on January 2016, and received a certificate of completion inspection on March 21, 2016 regarding the instant construction.

C. Upon the Plaintiff’s request, the Defendant opened an account under the name of the Defendant, and deliver the check to the Plaintiff and deposit money to the said account.