(영문) 의정부지방법원 2011.05.26 2010가합6793

설계용역비

Text

1. The plaintiff's claim is dismissed.

2. The costs of lawsuit shall be borne by the Plaintiff.

Reasons

1. Basic facts

A. On August 4, 2008, the Defendant announced a public announcement of the shop design service (hereinafter “instant service”) with respect to the construction project of the B Ilwon C Welfare Center (hereinafter “instant project”), and the Plaintiff was selected as the successful bidder of the instant service.

B. On August 20, 2008, the Plaintiff entered into a working design service agreement with the Defendant, which includes the following:

(1) The term "the first contract of this case" means the service contract amount: 69,007,80 won for the service contract for the construction of a welfare center: 90 days after the commencement of the work; 90 days after the commencement of the work; 90 days after the commencement of the work; and 90 days after the commencement of the work: on August 22, 2008, the summary of the work: < Amended by Presidential Decree No. 21100, Nov. 2008; - the working design for the welfare center - the working design for the construction project - the scale of the construction: the total floor area: 1,700 square meters; 1,00 square meters; 3rd underground floors (1), reinforced concrete; 90,000 won from the commencement of the work; 1,75,000 won; - the preparation of the work plan and the implementation guidelines for the construction project within the scope necessary for the execution of the construction project (hereinafter referred to as the "execution guidelines for the construction project plan and the construction project plan").

- Delivery of design documents: The quantity of design documents for each stage of execution design under annexed Table 2 of “Scope of and price standards for certified architect services (No. 2002-270, Oct. 15, 2002),” must be supplied.

Report on commencement of services by phase of business - After contract.