(영문) 대전지방법원 2019.08.28 2019가단105143

구상금

Text

1. The Defendant’s KRW 1,406,073,865 and KRW 967,912,289 among the Plaintiff’s KRW 1,406,073,865 shall be from September 16, 2008, and KRW 411,810,636.

Reasons

1. Basic facts

A. (1) The plaintiff filed a lawsuit against the defendant and B farming association corporation, C, D, and E in around 209 against the defendant and the Seoul Central District Court 2009Gahap21770 (hereinafter referred to as "the Seoul Central District Court) In the above case 2009Gahap2170, B farming cooperative is the principal debtor, and the defendant, C, D, and E are jointly and severally and severally a joint surety and severally a joint surety of 1,51,711,62 won [the maximum amount of KRW 850,000,000, KRW 525,610,597 - KRW 4,05,050 [the maximum amount of KRW 460,00,000, KRW 407, KRW 2076, KRW 2076, May 26, 200 (hereinafter referred to as "the first credit guarantee reserve - the credit guarantee reserve - the amount of credit guarantee - the amount of credit guarantee 205407.27.4

【The Defendant and B farming association, C, D, and E are jointly and severally liable to pay to the Plaintiff 98,740,359 won out of the amount of subrogated payment of KRW 522,452,80,00 (3,886 won for the amount of KRW 1,362,630) and the amount of delay compensation for the amount of KRW 1,51,711,62, and the amount of KRW 988,740,359 from September 16, 2008 to April 30, 2008 to the effect that the amount of KRW 15% per annum from the following day to the date of full payment (hereinafter “instant judgment”), and the judgment against the Defendant 180,000 won was finalized with respect to the amount of KRW 1,511,711,604,747, and the amount of money calculated at a rate of 20% per annum from the next day to the date of full payment.

B. The Plaintiff’s partial recovery of the Plaintiff’s claim was recovered from KRW 109,794,111 out of the remaining amount of subrogated payment for the first guarantee after the judgment of the previous suit in this case, and collected KRW 20,828,070 out of the remaining amount of subrogated payment for the second guarantee. The remainder of the amount of subrogated payment for the second guarantee is KRW 445,459,489, and the amount of subrogated payment for the second guarantee is KRW 41,810,636.