beta
(영문) 인천지방법원 부천지원 2018.01.24 2017가단2849

손해배상(기)

Text

1. The Defendants are within the scope of property inherited from the network D (E).

A. Plaintiff (Appointed) Co., Ltd.

Reasons

A. The Plaintiff (Appointed Party; hereinafter “Plaintiff”) entered into a construction contract between the network D (hereinafter “the network”).

2) The judgment of the court below is justifiable. It is so decided as per Disposition by the assent of all participating Justices on the bench

(2) On December 22, 2015, the construction project area entered into a construction contract with the Deceased as follows (the original intent is omitted to the extent that is not undermined and the clerical error is corrected). The construction project area: 132 square meters: 170,000 square meters: 190 square meters: 20% at the time of commencement of the construction project (excluding value-added tax): 40% at the time of completion of the H beam board, 10% at the time of completion of the construction project (the completion of use) and 10% at the time of completion of the construction project (the completion of the construction), 10% at the time of completion of the special agreement (the submission of performance bond): The construction and civil drawings shall correspond to the construction and civil engineering drawings, electricity, fire-fighting, landscaping, landscaping, fume, fume, fume, and paths: 90 days after the commencement of the construction project, the construction project shall be based on drawings, and the construction project area shall always be divided into the owner and the Plaintiff’s construction project site (the Plaintiff).

(A) The contract between the plaintiff globalr and the deceased ("the contract of this case" is the same as the above contract of this case)

(B) A contract between the Plaintiff A and the Deceased (hereinafter “instant two contract”) between the Plaintiff A and the Deceased for the construction cost of KRW 60,000,000 square meters of the building area of 132 square meters and the construction cost of KRW 110,00,000 of the construction cost of KRW 190 square meters of the building area (Additional tax) (hereinafter “instant two contract”).

B. 1) The Deceased’s implementation of the construction contract, etc. (i) pursuant to each of the instant construction contracts, and thereafter, pursuant to each of the instant construction contracts, the first-class neighborhood living facilities (retail stores) of the G general steel structure (hereinafter “instant two buildings”).

....