beta
(영문) 수원지방법원평택지원 2014.12.10 2012가합7382

손해배상(기)

Text

1. As to KRW 2,011,317,685 among the Plaintiff and KRW 1,85,00,000 among the Plaintiff, the Defendant shall start from November 9, 2012, and KRW 156,317.

Reasons

1. The following facts do not conflict between the parties or may be acknowledged by taking into account the following facts: Gap evidence 1-1-2, Gap evidence 2-1-2, Eul evidence 3-1-4, Gap evidence 4-5, Gap evidence 7, Gap evidence 8-1-3, Gap evidence 9-1-3, Gap evidence 12-1-4, Gap evidence 13-1 through 3, Eul evidence 23-1-4, Eul evidence 24-3, Eul evidence 3, Eul evidence 10-1-3, Eul evidence 14, Eul evidence 24-1-3, Eul evidence 3, Eul evidence 10-5, Eul evidence 7, Gap evidence 8-1-3, Gap evidence 11-1-3, Gap evidence 12-1-3, Eul evidence 13-23, Eul evidence 24-1-3, Eul evidence 10, Eul evidence 10-2's testimony.

On October 5, 2011, when the Plaintiff constructed a factory on the ground of the previous factory site in Ansan-si (hereinafter “the previous factory site”) and operated a business, the registration conversion registration was completed on March 25, 201 with the land E, 7,811 square meters in Ansan-si E, Ansan-si, the area of the previous factory site was completed on March 25, 201. < Amended by Act No. 12327, Apr. 5, 2011; Act No. 10977, Apr. 7, 2011; Act No. 10937, Apr. 7, 2011; Act No. 10937, Apr. 5, 2011; Act No. 12934, Apr

In other words, among one parcel, 8,106 square meters (hereinafter “instant factory site”) was newly built on the ground of the newly established factory site, 4,03.05 square meters in total floor area, 3,610.05 square meters in manufacturing facilities, and 423 square meters in the size of auxiliary facilities (hereinafter “instant factory site”) and filed an application under Article 13(1) of the Industrial Cluster Development and Factory Establishment Act (hereinafter “instant application”) and the Defendant accepted the said application and approved the alteration of factory (hereinafter “instant disposition”). < Amended by Act No. 1034, Aug. 9, 2010>

B. On September 1, 2010, the Plaintiff entered into a contract for the construction work of KRW 3,100,000,000 of the construction amount with Dance Construction Co., Ltd. for the new construction of the instant factory, and entered into a contract for the electrical construction work of KRW 610,00,000 of the construction amount with Djin Electricity Co., Ltd., and entered into the contract for the new construction of the instant plant with the said company, and the said company all of the construction