보증채무금
1. The Defendants shall jointly and severally serve as KRW 1,00,000,000 on the Plaintiff and as a result, from April 1, 2015 to January 26, 2016.
1. The description of the grounds for the claim shall be as specified in the attached Form;
(2) Judgment by public notice of applicable provisions of Acts (Article 208 (3) 3 of the Civil Procedure Act)
3. Some dismissed parts of the Plaintiff claim for damages for delay calculated at the rate of 20% per annum from the day following the last delivery of the copy of the instant complaint to the day of complete payment. However, the statutory interest rate provisions of the main sentence of Article 3(1) of the Act on Special Cases Concerning Expedition, etc. of Legal Proceedings were amended by Presidential Decree No. 26553, Sept. 25, 2015 to 15% per annum, and were enforced from October 1, 2015, the portion claiming damages for delay calculated at the rate of exceeding 15% per annum from the day following the last delivery of the copy of the instant complaint to the day of complete payment is without merit.