(영문) 인천지방법원 2019.08.23 2019가합50464

대여금

Text

1. The Defendant’s KRW 1,00,000,000 as well as 15% per annum from May 11, 2019 to May 31, 2019 to the Plaintiff.

Reasons

1. On December 30, 2013, the Plaintiff borrowed KRW 1.5 billion to the Defendant, but the Defendant paid only KRW 500 million on January 29, 2014, and did not pay the remainder of KRW 1.00 billion.

Therefore, as the Plaintiff seeks, the Defendant is obligated to pay to the Plaintiff 1 billion won the above loan and damages for delay calculated at the rate of 15% per annum from May 11, 2019 to May 31, 2019, and 12% per annum from the next day to the day of full payment.

2. Judgment by public notice of applicable provisions of Acts (Article 208 (3) 3 of the Civil Procedure Act);