(영문) 서울서부지방법원 2015.12.18 2015가단203625

공사대금

Text

1. The Defendant: (a) KRW 79,860,000 for the Plaintiff and its related KRW 5% per annum from October 1, 2013 to November 4, 2014; and (b) November 5, 2014.

Reasons

1. Basic facts

A. On June 12, 2013, the Plaintiff concluded a contract with the following contents (hereinafter referred to as the “instant contract”) on the part of the managing office of the set-off zone 2 apartment complex apartment complex management office (hereinafter “management office”) entrusted with the Defendant’s duties, which is the managing office of the set-off zone 2 apartment complex apartment complex management office (hereinafter “instant apartment complex management office”). The Plaintiff concluded a contract for construction cost of KRW 266,200,000 (including value-added tax).

(1) “A”, “B”, “A”, “B”, “A”, “A”, “A”, “I shall, in principle, accept the design drawings, electrical specifications, etc. presented by “A” as part of the contract and carry out the construction in compliance with the instructions and requests of the supervisor designated by “A”. Article 3 (Period of Construction) : (2) The term “A”, “A”, “A”, “within 00,000 won from the present portion of the construction cost,” “within 50,000,000 won from the present portion of the construction cost, 60,000,000 won from the present portion of the construction cost, 60,000,000 won from the present portion of the construction cost, 60,000,000 won from the present portion of the construction cost, 60,000,000 won from the date of completion (60,000,000 won from the date of completion (660,0,066,060,0,060,0,0,0,0600,0