beta
(영문) 서울남부지방법원 2015.01.23 2013가합10964

공사대금 등

Text

1. The Defendant-Counterclaim Plaintiff (Counterclaim Defendant) each of KRW 1,695,060 against the Plaintiff (Counterclaim Defendant) and its related amount from June 6, 2013 to January 23, 2015.

Reasons

A principal lawsuit and a counterclaim shall be deemed simultaneously.

1. The following facts (additional matters) may be paid after deducting the total amount of KRW 72 million from the payment of the balance at the time of the waiver of the construction work by a contractor;

(contractors are not entitled to legal response). Materials shall be constructed in the same way as domestic E interior drawings.

A parking lot, the condition of the installation of a corridor construction (the subsequent estimate) - the condition of the installation of a parking lot, the condition of the installation of a corridor construction - the content of the 65 million won standard special agreement, 1) the contractor shall execute (all construction works) the multi-story design (the contractor). 2) the contractor may request reconstruction when domestic use of the material

A. On August 4, 2012, the Plaintiff was awarded a contract with Defendant C for the construction cost of KRW 256 million for the interior work of the interior telecom work of KRW 20,000,000,000,000,000,000,000 from Defendant C and two Dongs and 16,000,000,000,000.

(B) The Defendants are obliged to pay the construction cost in installments each of the amounts of KRW 128 million (hereinafter “instant construction”). The following are added to the contract made at the time, and the following is attached to the other matters:

[Other Matters]

1. The section of the interior of the guest room shall be inside the guest room;

6. The interior works for the management office and the staff lodging room shall be implemented by the contractor, and it shall not be included in the construction cost (the contractor shall perform the services); 7. The multi-story interior works shall be implemented by the contractor; and 7.2 million won, excluding the 18.0 million won per unit at the request of the contractor when the contractor renounces the multi-story construction works at the request of the contractor, may be paid after deducting the balance.

(the contractor is not entitled to any legal response). (b)

In addition to the management office and staff accommodation construction of the instant telecom, the Plaintiff spent KRW 30 million as construction cost.

On June 5, 2013, the Plaintiff completed the remaining construction works excluding the dudunes construction among the instant construction works.

C. The Plaintiff received advance payment of KRW 50 million and intermediate payment of KRW 160 million from the Defendants.

[Ground of recognition] There is no dispute.