(영문) 창원지방법원 2015.01.23 2014구합616

토지수용이의재결처분취소

Text

1. The Defendant’s KRW 3,252,80, and the Plaintiff’s annual rate of KRW 5% from October 7, 2014 to January 23, 2015.

Reasons

1. Details of ruling;

(a) Project approval and announcement 1) Project name: A river project (the project of this case) (the project of this case and restoration work on the rooftop; hereinafter referred to as the “instant project”);

(2) Notice: The project executor No. 2013-443 of the Haban Military Notice on May 17, 2013: the Defendant.

B. The subject matter of expropriation by the local land expropriation committee located on October 29, 2013: ① the land subject to expropriation is divided into 1,547 square meters in B-Yan-gun, Gyeongnam-gun, Gyeongnam-gun (C Seo-gun, 931 square meters in size), D 1,342 square meters in size (hereinafter each of the above accommodation land is divided into 2,779 square meters in size; hereinafter the above accommodation land is collectively referred to as the “land subject to expropriation”; and each of the above accommodation land prior to the division of the instant accommodation land is collectively referred to as “before expropriation.”

(2) The sum of the above obstacles, etc. (hereinafter collectively referred to as “the instant land burials”) and the compensation for farming loss on the ground B, and the compensation for farming loss on the D ground.

(2) The starting date of expropriation: Compensation for losses on December 18, 2013: ① 114,012,050 won for the instant land; ② 12,645,810 won for the instant land collection: Claim for expropriation and value-added compensation for the remaining land in the instant land: As to the instant land collection, the Plaintiff’s use of the remaining land in the past for the instant land cannot be deemed to have been significantly difficult, on the grounds that it is confirmed that there is no value decline.

5. An appraisal corporation: a uniform appraisal corporation and a joint appraisal corporation;

C. The Central Land Expropriation Committee’s objection No. 1 on February 20, 2014: (1) The amount of compensation for losses: ① the land expropriated in this case’s KRW 115,332,60, and ② the rejection of an objection against the land stolen in this case’s case’s case’s case’s case’s case’s case’s case’s case’s case’s case’s case of expropriation and depreciation compensation: The claim

3. Certified public appraisal corporations: New certified public appraisal corporations in the future of a stock company, and Aion appraisal corporations.

(d) this Court;