경쟁입찰참여자격취소처분취소 등
1. The plaintiff's claim is dismissed.
2. The costs of lawsuit shall be borne by the Plaintiff.
1. Details of the disposition;
A. The Plaintiff and the Plaintiff Company B (hereinafter “B”) are corporations that engage in the production, sale, etc. of high-Robbery concrete files (Phc file). B is the Plaintiff’s subsidiaries.
B. The Korea Primary concrete Industry Cooperatives (hereinafter “instant cooperatives”) consists of 17 companies including the Plaintiff producing phc files (the Plaintiff, B, and Dongjin Industries Co., Ltd., Ltd., Sungwon File Co., Ltd., Maump Industry Development Co., Ltd., Ltd., Ltd., order file file companies, epic file companies, Mur Industries Development Co., Ltd., Simsan Industries Co., Ltd., Simsan Industries Co., Ltd., Ltd., Ltd., Samsung C&M Co., Ltd., Ltd., Samsungyang Industries Co., Ltd., Ltd., Ltd., Ltd., Samsungyang Industries Co., Ltd., Ltd., Ltd., Inc., Ltd., and individual companies are specified in the name of a corporation with the exception of “stock company” and “limited company”).
C. On July 1, 2016, the representative director of the Plaintiff, and D, who is in office as the executive director in charge of business in C, the Plaintiff, and B, are the representative director of the Plaintiff, and D, in collusion with the executives of the instant union, the representative director of the instant member company, or the bid officer of the instant member company, by the prosecutor of the Seoul Central District Public Prosecutor’s Office on July 1, 2016, with respect to the case of the government-funded pHc file purchase bid between the instant association and its member companies from July 201 to May 24, 2016, the successful bidder was designated in advance and the premium company was invested in the amount of the pre-determined bid price and the premium company are to be reflected in the higher amount of the bid price, and the remaining company was to be awarded the successful bidder by the method of not participating in the relevant tender, or to be selected by the bid price by intentionally failing to participate in the bid, or by failing to independently select the successful bidder exceeding the estimated price.