구상금
1. Defendant Won Construction Co., Ltd. and Jin-jin Co., Ltd. jointly share with the Plaintiff KRW 111,532,968, whichever is 55,320.
1. Basic facts
A. On October 26, 2012, the Plaintiff entered into an insurance contract between the Plaintiff and the Construction and Distribution Co., Ltd. (hereinafter “Building and Distribution”), with respect to one of the crawlers (registration number: A; hereinafter “the instant crawer”) owned by the Construction and Distribution Co., Ltd., the Plaintiff entered into a heavy equipment safety insurance contract between the Plaintiff and the Construction and Distribution Co., Ltd. (hereinafter “Building and Distribution”), with respect to the insured’s building and distribution, the insurance period from October 28, 2012 to October 28, 2013, with respect to the crawer, with the indemnity amount of KRW 1.5 billion and the liability of KRW 350 million.
B. The process of the construction of the extension of the landing place in the national highway 1) Defendant Won Integrated Construction Co., Ltd. (hereinafter “Defendant Won Comprehensive Construction”).
(2) From the time of eternization to the time of eternization, e.g., the e., the e.g., the e., the e. the e., the e.
2) After being awarded the contract, the Defendant corporation (hereinafter “Defendant corporation”) was named as “Defendant Vietnam tower”).
2) In order to create a breakwater among the instant construction works, the instant concrete block was subcontracted for the process management of loading, unloading, and assembling of concrete block on the instant barge, and Defendant Jin-jin Co., Ltd. (hereinafter “Defendant Min-jin”).
(2) On July 9, 2013, Defendant Jin-J leased one barge (name C; hereinafter “instant barge”) from B, and Defendant Jin-J leased the instant tugboat from the National Distribution on September 25, 2013 to the construction site of each of the instant construction sites.
3. D, as a staff member of the dry Power Distribution, was put into the construction site of this case, and laid down the instant cater and concrete block on the instant barge at the pregrative emulgial emulgial emulgial emulgial emulgial emulgial emulgal, and performed the work of loading and unloading concrete block on the national highway.
C. On October 22, 2013, Defendant Jin-jin, who caused an accident, shall be transferred to the instant barge around 18:00.