(영문) 대구지방법원 2020.07.16 2019나311444

공사대금

Text

1. The part of the judgment of the court of first instance against the plaintiff, which orders payment below, shall be revoked.

The defendants are the defendants.

Reasons

1. Basic facts

A. On November 7, 2016, the Plaintiff, a company running the construction business, new construction business, etc. of housing, was awarded a contract for the construction of neighborhood living facilities (hereinafter “instant contract”) from Defendant B to Defendant B on the ground outside Daegu-gun, Daegu-gun, and one ground (hereinafter “instant construction”) (hereinafter “instant contract”), and its main contents are as follows.

The date of commencement: The scheduled date of completion on November 10, 2016: The total cost on March 30, 2017: 292,60,000 won (including value-added tax): the rate of liquidated damages for delay: the external wall with modified 0.1%: the change to the Ministry of Requisition.

B. On June 14, 2017, the Plaintiff prepared a completion agreement with Defendant B and agreed as follows (hereinafter “instant completion agreement”). On the lower end of the instant completion agreement, the Plaintiff signed the phrase “Joint Guarantee C” and Defendant C’s signature.

B and B (Plaintiffs) agree as follows, according to the completion of construction of the building of the Si-gu Daegu Metropolitan City E (Neingu Living Facilities) of the quasi-public partnership, as follows:

A) A does not require the contractor to re-conform all the materials used in the construction as at present, except any defects arising from the construction of a building. (ii) No objection is raised against all the materials used in the construction.

3) A and B shall pay 3,000,000 won (Won 33,00,000), including value-added tax, to B, and the balance shall be paid at the same time as the bank loan after completion. The following construction defects as required by A are reconstruction: (a) the balance Won 24,00,000 (AT separate) are reconstruction:

When replacing the 1st floor railer by the main stairs of the entrance, the error other than the material used in the construction shall comply with the contract, in addition to the 33,000,000, added tax, etc. (including the 33,000,000, added tax) under the 2nd gate of the floor container handling stairs between the floor waterproof and the columns, and the 2nd gate of the net container handling stairs between the columns, and the 33,00,000,000,000, and at the same time as the seal is affixed on the completion of this agreement, shall be submitted to the design office.

this paper.