(영문) 광주지방법원목포지원 2015.01.23 2013가단5471

손해배상(기)등

Text

1. The Defendant: (a) KRW 33,710,000 for the Plaintiff and 5% per annum from May 25, 2013 to January 23, 2015.

Reasons

1. Determination as to the cause of claim

가. 기초사실 (1) 변압기의 1차 폭발 원고는 전기공사업체로서 2012. 12월경 ㈜신안천사김(이하 ‘소외 회사’라 한다) 운영의 전남 신안군 압해읍 학교리 132-9 소재 김 공장 신축현장에 전기시설공사를 시공함에 있어, ㈜하나전기로부터 피고 제조의 변압기(표준 몰드 TR 3Φ 2,500KVA)가 포함된 수배전반설비 및 분전함을 공급받았다

(5) On the other hand, in the first floor electric room in December 28, 2012, the above company was supplied with the above company to the company in charge of the company in charge of the company in charge of the company in charge of the company in charge of the company in charge of the company in charge of the company in charge of the company in charge of the company in charge of the company in charge of the company in charge of the company in charge of the company in charge of the company in charge of the company in charge of the company in charge of the company in charge of the company in charge of the company in charge of the company in charge of the company in charge of the company in charge of the company in charge of the company in charge of the company in charge of the company in charge of the company in charge of the company in charge of the company in charge of the company in charge of the company in charge of the company in charge of the company in charge of the company in charge of the company in charge of the company in charge of the company in charge of the company in charge of the company in charge of the company in charge of the company in charge of the company.

Accordingly, the defendant dispatched employees B to the site following the day, and B, after examining the causes of explosion and undergoing the meetings of the persons concerned with the future countermeasures, and in response to the demand of the non-party company, damage caused by the explosion of the pressurer.