beta
(영문) 대전지방법원 2017.06.14 2015가합106824

손해배상(기)

Text

1. The Defendant (Counterclaim Plaintiff) paid KRW 70,350,000 to the Plaintiff (Counterclaim Defendant) and its related amount from May 7, 2015 to June 14, 2017.

Reasons

. By November 15, 2014

(2) The term “the second construction contract” refers to the following: (a) the term “the term “the term “the term “the term “the term “the term “the term “second construction contract”; and (b) the term “the term “the term “the term “the term” means the term “the term “the term “the term “” under the term “second construction contract”; and (c) the term “the term “the term “the term” under the term “the term “three million won” under

(b) “alternatives”;

1. It is required to pay a million won as a steel contract simultaneously with this contract;

At the time of completion of the structural construction of multi-household and completion of the structural construction of the 3-dong 3-dong Gain, Dong-do 401, Dong-dong Do-dong Do-dong Do-dong Do-dong Do-dong Do-dong Do-

2. The sn beamline of the sn beamline shall complete the transfer of registration of 202, with the sn beamline of the sn beam and the sn beam of the multi-household.

3. At the time of completion of the center and the interior of the multi-household, the relocation of 402 House shall be completed;

4. The relocation of registration shall be completed in consultation with the family room when the completion of various authorization and permission is completed.

* In the event that construction is delayed or suspended without any natural disaster, 60 = 210 million = 210 million won, all responsibilities arising from the delay or suspension of construction for multi-household housing are made to the employer (defendant).

When the construction work is discontinued, the remaining construction work shall be transferred to the other contractor, without raising any objection, and the purpose of the owner shall be the owner.

On September 30, 2014, the Plaintiff and the Defendant agreed on the payment method of the construction price under the second construction contract as follows:

All responsibilities arising from delay and suspension of construction without any natural disaster shall be borne by the contractor to the defendant.

5/100 for liquidated damages shall be excluded from the construction amount.

The above matters shall be separate from the construction contract.

On October 10, 2014, the Plaintiff and the Defendant agreed on the compensation for delay for the said construction works as follows:

However, the defendant, while performing the second construction, completed only the aggregate construction around October 10, 2014 and discontinued the remaining construction work at the site.