대여금
1. The Defendant shall pay to the Plaintiff KRW 160,00,000 and the interest rate of KRW 20% per annum from June 19, 2015 to the day of full payment.
The plaintiff asserts that on August 30, 2005, the cause of the claim of this case, the defendant lent KRW 160,000,000 to the defendant on September 30, 2006 after fixing the due date for payment as of September 30, 2006. The defendant is deemed to have led to confession under Article 257 of the
Therefore, the defendant is obligated to pay to the plaintiff 160,000,000 won and damages for delay at the rate of 20% per annum from June 19, 2015 to the date of full payment as requested by the plaintiff, which is obvious from June 19, 2015 that the delivery date of a copy of the complaint of this case is the day after the above payment period. Thus, the plaintiff's claim of this case seeking this payment shall be accepted for the reasons, and it is so decided as per Disposition.