건물명도
1. The instant lawsuit was concluded on June 28, 2015 as deemed the withdrawal of the lawsuit.
2. The costs of the lawsuit after the request for setting the date.
The fact that the Plaintiff was absent on May 13, 2015, despite being served with the notice of the date of first pleading on March 24, 2015, and that the Plaintiff was absent on the date of second pleading on May 19, 2015, and that the Plaintiff was absent on May 27, 2015, despite being served with the notice of the date of second pleading on May 19, 2015; the Defendant was present on the date of second pleading and did not present each pleading; the fact that the Plaintiff did not file an application for designation of date within one month from the date of second pleading and submitted an application for designation of date by submitting the “application for designation of date” on July 6, 2015 is apparent.
According to the above facts, the instant lawsuit was concluded on June 28, 2015 when one month has elapsed from the date of the second pleading pursuant to Article 268 of the Civil Procedure Act as deemed the withdrawal of the Plaintiff’s lawsuit.
As such, a declaration of termination of the lawsuit in this case is made.