1. The plaintiff's claims against the defendants are all dismissed.

2. The costs of lawsuit shall be borne by the Plaintiff.

Reasons

(c).. c.

On June 11, 2003, the Plaintiff Association’s inaugural general meeting 1) The Plaintiff Association shall have the consent to the rebuilding resolution and the project plan on June 11, 2003, the enactment of the rebuilding association regulations, etc. at the inaugural general meeting of the Association (hereinafter “Inaugural general meeting”).

(2) The main contents of the “resolution and project plan” approved at its inaugural general meeting are as follows:

The design outline (it may be changed in the process of authorization and permission, and it shall be determined at the time of the approval of a project plan) of the new building - The area on the public register: 160,461.20 square meters (48,539.51 square meters): 157,779.10 square meters (47,728.18 square meters): - The total floor area of the new building: 557,049.50 square meters (168,507.47 square meters): - the floor area ratio: 274.47%: the scale of the apartment: the estimated amount of expenses required for the removal of the existing building or welfare facilities, and for the construction of the new building; the construction cost of the new building - the construction cost of 3,351,500,000 won - the construction cost of the new building - the construction cost of 5.35 billion won or more; the construction cost of the new building - the construction cost of - the changed project area - the total of 261.4.6 billion billion.

◎ 시공자와 공사계약방식은 지분제(대물변제) 방식으로 한다.

◎ 국공유지 매입이 있는 경우 매입한 토지는 조합원 소유 종전의 등기상 대지지분 면적을 기준으로 배분ㆍ귀속하며 그 비용의 부담은 시공자와의 계약에 따른다.

◎ 사업비는 아파트 등의 일반분양수입금과 조합원의 부담금 등으로 충당한다.

◎ 조합원의 권리지분 및 부담금은 아래와 같이 산정함을 원칙으로 한다.

Provided, That this shall not apply where separate rights shares and charges are determined in a management and disposal plan.

. Members of the apartment ownership association.