손실보상금
1. The Defendant: 3,096,890 won for Plaintiff A; 17,405,10 won for Plaintiff B; 14,900,000 won for Plaintiff C; 14,900,000 won for Plaintiff D, E, and F.
1. Details of ruling;
(a) Project approval and public announcement - Project name: G Housing redevelopment and rearrangement project (Ij): Defendant - A public announcement of project approval: H of Eunpyeong-gu Seoul Metropolitan Government on May 21, 2015;
B. The adjudication of expropriation made by the local Land Tribunal on May 25, 2018 - Plaintiff A, Eunpyeong-gu Seoul Metropolitan Government I large 175 square meters (hereinafter “I land”) and all obstacles, such as the above land and above-ground buildings (hereinafter “I obstacles”) were the partitioned sections of the building on the ground of Eunpyeong-gu Seoul Metropolitan Government J ground K, and the share of the site was assessed as a whole with the building.
(hereinafter referred to as “J” ): Plaintiff C. 1/3 equity of the land of Eunpyeong-gu, Seoul: 149 square meters (hereinafter referred to as “L-based land”): 32,917, B.70,700, 000 won and/or 122 square meters (hereinafter referred to as “M”): 1/3 equity of the land of Eunpyeong-gu, Seoul: 1/3 equity and/or 1/3 equity of Plaintiff E., 1/3 equity and/or 1/3 equity of Plaintiff F. M: 497, 525,00 I: 32,917, 32,70,000 won and/or 1: Plaintiff M. 666,00 won and/or 63 equity and/or 65 equity and/or 1/668,70,000 won and/or 1/667,00 won and/or 360,000 won and/67,00.