구상금
1. The part of the judgment of the court of first instance against the plaintiff corresponding to the amount ordered to be paid below shall be revoked.
The defendant.
1. The reasoning of the court's explanation concerning this case is as follows, except for the reasons for this case from No. 11, No. 13, and No. 12, No. 13, and No. 12, the court's explanation is as stated in the reasoning of the court's decision of the first instance. Thus, it is accepted by the main text of Article 420 of the
3) In addition to the Plaintiff and the Defendant’s reasons for fault ratio and amount of reimbursement prior to the Plaintiff and the Defendant’s liability, the direct causes of the instant accident are as follows: (a) the Defendant left away on the road immediately adjacent to the road where the Defendant would naturally have violated the instant contract and caused the Defendant to neglect for long time without taking sufficient safety measures; (b) the Plaintiff’s reason for liability was not properly supervised the Defendant’s breach of the Defendant’s duty of care; (c) from the standpoint of the Plaintiff who should manage a large number of construction sites conducted within his jurisdiction, such as roads in Seoul Special Metropolitan City, etc.; and (d) it appears not to have been easy for the Defendant to become aware or prevent the occurrence of an accident in advance due to the Defendant’s breach of the said duty of care; (d) it is reasonable to deem that the Plaintiff and the Defendant’s fault ratio is 10% and 90%; (e) the specific burden of the Plaintiff’s fault ratio is 46,878,190 won (=468,781,90%) and the Defendant’s fault ratio.
C. As to the Plaintiff’s share of KRW 421,903,710 and KRW 281,269,140 which was already cited in the judgment of the first instance, the Defendant’s lawsuit promotion, etc. regarding the existence and scope of the Defendant’s obligation from March 29, 2017 to June 21, 2018, which is reasonable for the Plaintiff to dispute as to the existence and scope of the Defendant’s obligation to pay damages to A, etc., from March 29, 2017 to June 21, 2018.