beta
(영문) 춘천지방법원 2016.08.09 2015가단51190

소유권이전등기

Text

1. All applications for participation by independent party intervenors shall be dismissed;

2. The defendant is the plaintiff corporation.

Reasons

1. Facts of recognition;

A. While the Defendant and the Dongcheon-gun Group Co., Ltd. agreed with the Defendant on the agreement with the Dongcheon-gun Group Co., Ltd., Ltd., the Dongcheon-gun Group Co., Ltd., Ltd. (hereinafter referred to as the “Dongcheon-gun Group”) designated the Dongcheon-gun Group Co., Ltd., Ltd. (hereinafter referred to as the “Dongcheon-gun Group”) as the project implementer on July 4, 2008, and on June 4, 2008, the Dongcheon-gun Group Co., Ltd. (hereinafter referred to as the “Dongcheon-gun Group”) on behalf of the Defendant to relocate the H facilities located at the time of the project plan, and on behalf of the Defendant to transfer the relocation project and the expenses therefrom, the Dongcheon-gun Group Co., Ltd., Ltd. (hereinafter referred to as the “instant project”).

나. 피고와 원고 주식회사 오라클골프리조트의 약정 등 (1) 이 사건 사업의 공동시행자는 원고 주식회사 미라클팰리스(이하 '원고 미라클‘이라고 한다), 주식회사 F(대표이사 I)(이하 ‘F’라고만 한다), 동춘천컨트리클럽이었는데, 피고는 2009. 9. 30.경 원고 주식회사 오라클골프리조트(이하 ‘원고 오라클’이라고 한다), 원고 미라클, F로 변경 승인하였다.

(2) Accordingly, on December 2009, Plaintiff Oracle and F succeeded to the obligation owed to the Defendant by the same Chuncheon consortium pursuant to the agreement entered in the above Paragraph (1) with the Defendant. The Plaintiff Oracle succeeds to the Plaintiff’s land (1,039,375 square meters) and facilities, including the land of 57 square meters (1,039,375 square meters (hereinafter “instant real estate”) and the land of 159,670 square meters (hereinafter “instant real estate”) and the land of 57 square meters (hereinafter “instant real estate”).