(영문) 서울중앙지방법원 2021.02.03 2020가합509718

물품대금

Text

1. Defendant B’s KRW 275,577,320 as well as 6% per annum from January 3, 2020 to January 13, 2020, respectively, to the Plaintiff.

Reasons

1. Plaintiff’s claim against Defendant B

A. A. The summary of the parties’ assertion (1) concluded a contract with Defendant B on March 2013 for the manufacture and sale of the bicycle and bicycle parts (hereinafter “instant agency contract”). Defendant B supplied the goods, such as bicycle and bicycle parts (hereinafter “instant goods”). Defendant B did not pay part of the price of the goods to the Plaintiff until January 2, 2020, and did not pay the remainder of KRW 275,577,320 (hereinafter “the price of the instant goods”). Defendant B is obligated to pay damages for delay from January 3, 2020, following the date of January 2, 2020.

(2) 피고 B ㈎ 피고 B은, ① 2019. 4. 경 원고에게 1억 원을 변제하였고, ② 2019. 8. 경부터 원고에게 매월 100만 원씩 변 제하고 있으며, ③ 2019. 3. 13. 원고에게 83,476,500원 상당의 이 사건 물품을 반품하였고, ④ 2019. 3. 31. 이후로는 원고로부터 이 사건 물품을 공급 받지 않았으므로, 원고가 주장하는 거래 내역이나 이 사건 물품대금을 인정할 수 없다.

㈏ 원고는 2018. 7. 경부터 일방적으로 피고에 대한 물품공급을 중단하고 피고 B의 거래처에 직접 물품을 공급하였고, 피고 B에 대하여 재고조사를 한 후 358,396,195원의 반품 세금 계산서를 발행하여 피고 B은 부가 가치세, 종합 소득세 등 세금을 3억 원 가량 납부하여 손해를 입었다.

B. The following facts are recognized in light of the respective descriptions (including branch numbers) of evidence Nos. 1 through 3, 5, 11, and 12, and the purport of the entire pleadings.

(1) On March 23, 1979, the Plaintiff was established for the purpose of manufacturing and selling various bicycles, and was operated by Defendant B around March 2013.