수용보상금증액 청구의 소
1. The defendant shall pay to the plaintiffs each amount of money and each of the above money stated in the attached Form 1 compensation statement.
1. Details, etc. of ruling;
(a) Project name: Public announcement of project approval (G industrial complex development project) for an industrial complex development project: The defendant;
B. Subject to the expropriation ruling by the Central Land Tribunal of Gyeongbuk-do on July 27, 2018 (hereinafter “adjudication of expropriation”): Each land and obstacles indicated in the attached Table 1 of the details of compensation in the Plaintiffs’ Schedule to the Gyeongbuk-gun, Gyeongbuk-do, which are owned by the Plaintiffs (hereinafter collectively referred to as “instant land and obstacles”).
(2) The starting date of expropriation: Compensation for losses on September 20, 2018: The amount indicated in the column for “adjudication of expropriation” in the attached Table 1 compensation details. (c) The Plaintiffs received compensation pursuant to the Defendant’s adjudication of expropriation during the period from October 2, 2018 to November 30, 2018. (d) The Central Land Expropriation Committee’s ruling of objection on April 25, 2019 (hereinafter “adjudication of expropriation”).
(E) Compensation for losses: The amount indicated in the separate sheet on the details of compensation for losses: (e) the amount indicated in the separate sheet on the appraisal of the appraiser J. As a result of the court’s entrustment of appraisal to the appraiser J. The same is as stated in the separate sheet on the statement on compensation for losses: The amount indicated in the separate sheet on the “court appraisal” in the separate sheet on the statement on compensation for losses for losses.
2. The assertion and judgment
A. Since the reasonable compensation for the land and obstacles of the plaintiffs' assertion is based on the court's appraisal, the defendant is obligated to pay the plaintiffs the difference between the above legitimate compensation and the compensation due to the defendant's ruling of expropriation, and damages for delay from the day after the date of commencement of expropriation.
(b) The details of the relevant statutes are as shown in Appendix 2.
C. The appraisal results submitted by an appraiser under the entrustment of the court of relevant legal principles on the basis of professional knowledge and experience are considerably important in the process.
or the other party.