(영문) 수원지방법원 2019.04.18 2017가단548806

손해배상(산)

Text

1. The Defendants jointly share KRW 38,651,640 with respect to the Plaintiff and KRW 5% per annum from March 17, 2017 to April 18, 2019.

Reasons

1. Facts of recognition;

A. Defendant B Co., Ltd. (hereinafter “B”) subcontracted the removal of existing buildings (hereinafter “instant building”) among the construction of an urban studio-type building located in Yongsan-gu E to F on March 10, 2017.

B. On March 14, 2017, F subcontracted Defendant C Co., Ltd. (hereinafter “C”) with respect to the removal of the sand position plate (hereinafter “instant construction”) among the entire removal works.

C. On March 17, 2017, the Plaintiff, an employee of Defendant C, together with other workers, was engaged in the work of moving the first floor of the instant building to a panel (hereinafter “instant work”). On the other hand, the net floor of the roof of the instant building was cut down below the lower floor while moving the board.

(hereinafter “instant accident”). The instant accident brought injury to the Plaintiff, such as the pressure frame of the First Twitter, the pressure frame of the Second Twitter, the Third Twitter, and the pressure frame of the Second Twitter, and the left-hand string.

After the instant accident was issued, the Plaintiff and other workers employed by the Plaintiff examined the studio of the roof after the instant accident was issued, it was clear that the Plaintiff and other workers laid the studio on March 16, 2017, which was the day before the instant accident occurred.

E. Defendant C provided a safety mother to the Plaintiff, but did not pay safety equipment, such as safety belts, and did not provide safety education properly.

In addition, there was no safety device, such as a work engine, a fall-protection network, etc., at the accident site of this case.

F. The Plaintiff was paid KRW 16,68,820 for temporary layoff benefits (from March 17, 2017 to November 5, 2017) from Korea Workers’ Compensation and Welfare Service, KRW 11,823,620 for medical care benefits, and KRW 30,353,40 for disability benefits.

[Reasons for Recognition] Facts without dispute, Gap evidence Nos. 1 through 6, Eul evidence Nos. 1 through 10 through 12, and the purport of the whole pleadings.