건물등철거
1. Defendant C Co., Ltd.:
(a) Indication 1, 2, 2 of the annexed drawings among the real estate indicated in the annexed real estate.
1. Basic facts
A. The Plaintiff is the owner of the instant forest land. 2) The Plaintiff and the Defendant C Co., Ltd. (hereinafter “Defendant Co., Ltd.”) (hereinafter “Defendant Co., Ltd.”) entered into a lease agreement with the Plaintiff on July 30, 2015, with respect to the portion (A) 1,00 square meters inside the instant forest, which was connected in order to each point of subparagraph (a) of 1,12,00,00,000 square meters of forest land in Seo-gu Incheon, Seo-gu, Incheon (hereinafter “the instant forest land”). From among the instant forest land, the Plaintiff and the Defendant C Co., Ltd. (hereinafter “Defendant Co., Ltd.”) entered into the lease agreement with the Plaintiff, the lessor, the lessee, the Defendant Co., Ltd., Ltd., for the lease agreement with the Plaintiff from August 1, 2015 to August 13, 2015 (hereinafter “the instant lease agreement”).
3) Around January 8, 2016, the Defendant Company sent to the Defendant Company a document stating that “the termination of the instant first lease contract on the ground of rent delay” was the monthly and December of the same year according to the instant first lease contract. On January 11, 2016, the said mail was served to G, the representative of the Defendant Company, by content-certified mail.
5) On the ground of the part (i) part of the instant forest connected in sequence with each point of indication 1, 2, 9, 5, 6, 7, 8, 1, and 1 of the annexed drawings among the instant forest land, there are 350 square meters at a single-story factory of the lightweight steel framed structure built by the Defendant Company. (b) Incheon Seo-gu, Incheon Metropolitan Government 820 square meters (hereinafter “the instant Before”)
1) Plaintiff B is the former owner of the instant case.
2) As to the instant lease agreement on August 7, 2015, Plaintiff B and Defendant D: (a) the lessor and Defendant D, the lessee, the deposit amount of KRW 7,000,000, monthly rent of KRW 500,000; and (b) the lease term from July 1, 2015 to June 30, 2017 (hereinafter “instant lease agreement”).
(b).