(영문) 부산지방법원 2016.06.28 2016가단21137

공사대금

Text

1. The defendant's KRW 60,000,000 for the plaintiff and 5% per annum from December 28, 2005 to April 24, 2006.

Reasons

1. Indication of claims: To be as shown in the attached Form;

2. A judgment without holding any pleadings (Articles 208(3)1 and 257 of the Civil Procedure Act): Provided, That the Plaintiff claims damages for delay at the rate of 20% per annum from April 25, 2006 to the date of full payment. However, the Plaintiff’s damages for delay seeking more than 15% per annum is dismissed, since the provision on statutory interest rate under the main sentence of Article 3(1) of the Act on Special Cases Concerning Expedition, etc. of Legal Proceedings was amended by Presidential Decree No. 26553, Oct. 1, 2015; and the provision on statutory interest rate was amended by Presidential Decree No. 26