공사대금
1. The plaintiff's claim is dismissed.
2. The costs of lawsuit shall be borne by the Plaintiff.
1. Basic facts
A. The Defendant’s contract for construction work 1) On June 28, 2016, to construct a church building C (hereinafter “C”).
) New D D D D D D D D D D D D D (hereinafter referred to as “instant construction”).
(2) On February 28, 2017, the Defendant entered into a contract for construction works, the construction cost of which is KRW 1.87 billion (the supply price of KRW 1.7 billion, value-added tax of KRW 170 million, value-added tax of KRW 170 million), and the construction period of which is from July 11, 2016 to February 28, 2017. (2) On February 28, 2017, the Defendant entered into a contract for construction works, the construction cost of which is KRW 2.0 million (the supply price of KRW 1.8 billion, value-added tax of KRW 1.8 billion, value-added tax of KRW 182 million, value-added tax of KRW 1.82 million), and the construction period of which is changed from July 11, 2016 to July 15, 2017.
(C) The Defendant paid C a total of KRW 20 million to C on September 8, 2016, KRW 230 million on October 31, 2016, KRW 200 million, KRW 100 million on November 1, 2016, KRW 3330 million on December 12, 2016, KRW 200 million on February 3, 2017, KRW 200 million on March 17, 2017, KRW 200 million on April 4, 2017, KRW 200 million on July 27, 2017, and KRW 700,000,000 on December 27, 2017.
) As to the instant construction works, the construction amount of KRW 176 million (the supply price of KRW 160 million, value-added tax of KRW 160 million, value-added tax of KRW 16 million) and the subcontract was concluded between August 1, 2016 and February 28, 2017 (hereinafter “instant subcontract”).
C) Of the instant construction works, there is a contract agreement between the Plaintiff and the Defendant on December 8, 2016 (Evidence 2-1) with the project owner, the Plaintiff, the construction business operator, the construction cost of KRW 90,20,000 (value of KRW 82,00,000,000), the construction period from December 12, 2016 to March 15, 2017; and the date of preparation as of December 8, 2016.
2. As to the additional works of fire-fighting systems among the instant construction works, only 46.2 millions of the project owner, constructor, and construction cost.