(영문) 의정부지방법원고양지원 2020.10.23 2019가합74686

공사대금

Text

1. The defendant shall pay to the plaintiff 153,641,345 won with 12% interest per annum from October 24, 2020 to the day of full payment.

Reasons

1. Fact-finding;

A. (1) On February 13, 2018, the Plaintiff entered into a contract with the Defendant for the construction of the instant factory (hereinafter referred to as “instant factory”) on a contract price of KRW 765,00,000 (excluding value-added tax) with respect to the construction of the instant factory (hereinafter referred to as “instant construction”) and the period of construction from March 1, 2018 to June 30, 2018 (hereinafter referred to as “instant contract”).

The main contents of the contract are as follows. The construction site for C-Newly constructed construction works of a factory: The date of commencement of the C-built construction works of the factory: The date of completion on March 1, 2018: the contract amount on June 30, 2018: Dolish Dolcheon,000,000 separate value-added tax (765,000) (excluding value-added tax).

6. Down payment: 150,000 won per day (in n.e., g., 150,000).

7. The first progress payment: the construction fund for the foundation and structure of the building - KRW 280,000 ( KRW 280,000).

8. Second progress payment: Iron/board/Telecommunications Corporation - Lee Ho-taen,00 won ( 280,000,000)

9. The third progress payment: The construction schedule and the detailed statement based on the design (including drawings, specifications, construction specifications, site descriptions, etc.; hereinafter the same shall apply) shall be submitted to the defendant, after concluding a contract and submitting a report on the commencement of construction works, until the time when the plaintiff submits a report on the commencement of construction works (including drawings, specifications, construction specifications, site descriptions, etc.).

Article 14 (Adjustment of Contract Amount Due to Modification of Design) (1) When the contents of the design do not coincide with the condition of the construction site, or are unclear, omitted or erroneous, or when there are errors in the construction site, or when the unexpected situation related to the construction occurs or the project plan is modified, the design shall

(2) Where an increase or decrease in construction volume occurs due to the modification of a design under paragraph (1), the contract amount shall be adjusted according to the following standards:

1...