beta
(영문) 의정부지방법원고양지원 2014.06.25 2013가합7677

전부금

Text

1. Defendant MS Construction Industry Co., Ltd. is entitled to set forth in [Attachment No. 3] set forth against the Plaintiffs.

Reasons

1. Basic facts

A. The Plaintiffs’ claim against H Co., Ltd. (hereinafter “H”) filed an order for payment with H on May 21, 2013 with the High Government Branch of the 2013th and 1095, H Co., Ltd. (hereinafter “P”) 81,106,120 won with the 23,435,256 won with the 17,312,300 won with the 17,212,951 won with the 20th 30, 300, 200, 300, 300, 17, 1375, 717, and 209 with the 20th 30, 200, 300, 300, 3000, 3000, 180, 196, 3010, 306, 306, 190, 3010, 196, 106, 106, 306, 36, 30.

B. On July 3, 2013, the Plaintiffs issued an assignment order of claims and assignment order (hereinafter “instant attachment and assignment order”) with the title of the instant payment order as the instant payment order and the assignment order was issued with H as the obligor, the Defendant as the garnishee, and as the third obligor, H as the goods-price claim against the Defendants. On July 8, 2013, the instant attachment and assignment order of claims was served on the Defendants, and was issued with the Defendant on August 22, 2013, the Defendant issued an assignment order of claims and assignment order with the Goyang Branch Branch 2013Kaga904 (hereinafter “instant attachment and assignment order”).