(영문) 서울중앙지방법원 2013.10.16 2012가합49617

용역비

Text

1. As to the Plaintiff’s KRW 770,00,000 and KRW 660,000 among them, the Defendant shall be from January 20, 2012, and KRW 110,00,000.

Reasons

1. Basic facts

A. The Defendant promoted an urban environment improvement project (hereinafter “instant project”) in which 5, Nammun-gu, Seoul (hereinafter “Seoul”) constructs buildings for business facilities in the area of 253 (hereinafter “instant area”) on June 1, 2009, and entered into a service contract for designation of an urban environment improvement zone (hereinafter “service contract for designation of an improvement zone”) with the Plaintiff’s performance of duties, such as formulation of maintenance plans, application for designation of an improvement zone, etc. in order to designate an urban environment improvement zone in the instant area, and ② Building design service contract (hereinafter “building design service contract”) with the content of performing duties related to the design of buildings to be constructed in the relevant area after the designation of the improvement zone. The main contents are as follows.

1) For the designation of the rearrangement zone in the instant area, the Plaintiff of the rearrangement zone designated service contract vicariously performs all the matters necessary for the improvement plan and the designation of the rearrangement zone under the Act on the Maintenance and Improvement of Urban Areas and Dwelling Conditions for Residents and Municipal Ordinances related to Seoul. In the event that the designation of the rearrangement zone in the instant area has been publicly announced and announced, the Defendant shall pay a total of KRW 500 million (No. 1) to the Plaintiff at the service cost (No. 1) (No. 2).

If the Plaintiff claims service costs to the Defendant in writing after completion of each phase of the above service, the Defendant completed approval for use of KRW 900,000,000 at the time of completion of construction deliberation (permission) at KRW 500,000 when a proposal for designation of the rearrangement zone was received at KRW 100,000,000 when a proposal for designation of the rearrangement zone was made under the following contract for the payment period of KRW 100,000 when the construction cost was completed at KRW 500,000 when the designation of the rearrangement zone was completed at KRW 1,00,000 when the construction cost was completed.