(영문) 울산지방법원 2018.07.05 2017구합6000

손실보상금

Text

1. The defendant,

(a) No. 2. Of the attached Form 2 calculation sheet to the plaintiffs, “n.e., the amount of discount” as stated in the column; and

B. Plaintiff A.

Reasons

1. Details of ruling;

(a) Business approval and public notice - Business name: Industrial complex development project (UU Corporation; hereinafter referred to as “instant project”) - Notice V of Ulsan Metropolitan City on December 3, 2015

(b) Adjudication on expropriation 1) Plaintiff A, B, C, D, E, and F (Adjudication by the Central Land Expropriation Committee as of November 10, 2016): Land the same as the No. 1 through No. 6 of the items to be expropriated - The date of commencement of expropriation: January 3, 2017 - Compensation for losses: the amount indicated in the column for “Adjudication on Expropriation” in attached Form 2: 2) Plaintiff G, and H (Adjudication by the Central Land Expropriation Committee as of December 8, 2016): - Land and obstacles such as the No. 7,8 of the items to be expropriated: The date of commencement of expropriation from January 31, 2017 - Compensation for losses: the amount stated in attached Form 2 “Adjudication on Expropriation” in attached Table 2.

3) Plaintiff I, L, M, N, O-type gathering, Q, R, S, T, J, and K (Adjudication by the Central Land Expropriation Committee on January 5, 2017): Land and obstacles as described in Nos. 9 through 19 from among the indications of goods subject to expropriation - the date of commencement of expropriation - Compensation for losses: February 28, 2017: the amount as stated in the column for “Adjudication of Expropriation” in attached Form 2: (c) Plaintiff A, B, C, D, E-type meeting, and F (Adjudication by the Central Land Expropriation Committee on April 27, 2017) - Compensation for losses: The amount as stated in attached Form 2 calculation sheet.

2) The adjudication of expropriation of Plaintiff G and H (the Central Land Tribunal’s adjudication on April 27, 2017) - Compensation for losses: The amount stated in the column for “B Interest” in the attached Form 2 calculation sheet; 3) Plaintiff I, L, M, N, O, P, Q, R, T, T, J, J, and K (the adjudication of May 25, 2017 by the Central Land Tribunal) - Compensation for losses: the amount stated in the column for “B Interest Adjudication” in the attached Table 2 calculation sheet.

[Ground of recognition] without any dispute, Gap evidence 2-1, 2, 3-1 through 8, Gap evidence 4-1, 2, and 5-1.